Kong's house, December 2009

Thanks to everyone interested in this project. For a description of the project, see first blog entry. - Tomoko

Summary

1/24/10 $450 wired for work on the concrete floors. Floors are finished now.
1/15/10 Sent email to friends about blog
1/12/10 Created House of Kong blog
1/11/10 Called Kong. Got more background info. and history
1/11/10 $200 wired for starting work on floors. An engineer/construction worker is scheduled to start on Jan. 15
1/1/10 Naoto tells me the story of Kong
12/31/09 Naoto returns from Laos

Monday, March 8, 2010

Here is the completed concrete floor that we funded. Next are the interior walls, toilet, sinks, electricity, windows and door, kitchen counters depending on the funding. There is still some left in the coffers for doing a few of these projects.

Thanks again to all.

No comments:

Post a Comment